Structural & Site Concrete
Summary
The cross-bid takeaway — overview, key findings, and recommendation.
Bidders
Ranked by price once any alternates that close scope gaps are added. Click a bidder to see what it covers.
Every line and every bidder in one full-screen sheet. Plug each gap with a suggested number or your own, and see every bid's leveled total.
Sections at a glance
Each bidder's total by section, including your plugs and corrections. Click a section to see every line in the sheet.
| Section | Tannerbrook Structural Concrete | Maplestone Concrete Constructors | Brindlewood Concrete Structures | Kestrel Ridge Concrete | Ironvale Concrete and Formwork |
|---|---|---|---|---|---|
01 10 00 · A. General requirements 5 lines | $241,200 1 open | $174,000 2 open | $238,500 complete | $240,000 4 open | $200,500 2 open |
03 30 53 · B. Foundations 3 lines | $803,900 complete | $902,000 complete | $808,300 complete | $1,012,000 complete | $771,650 complete |
03 31 00 · C. Slabs on grade 2 lines | $231,500 complete | $233,500 complete | $229,600 complete | $241,000 complete | $218,970 complete |
03 30 10 · D. Vertical concrete 2 lines | $611,100 complete | $611,000 complete | $626,200 complete | $618,000 complete | $590,100 complete |
03 30 20 · E. Elevated decks 3 lines | $1,213,000 complete | $1,203,000 complete | $1,226,600 complete | $1,238,000 complete | $1,155,000 complete |
03 20 00 · F. Reinforcing and post-tensioning 2 lines | $687,500 complete | $708,000 complete | $717,900 complete | $722,000 complete | $677,750 complete |
07 13 26 · G. Below-grade waterproofing 1 line | $85,000 complete | $98,500 complete | $109,500 complete | — 1 open | — 1 open |
03 30 30 · H. Stairs, curbs and pads 3 lines | $112,400 complete | $98,500 1 open | $117,200 complete | $119,000 1 open | $111,000 complete |
03 35 00 · I. Finishes and toppings 4 lines | $43,900 2 open | $59,500 2 open | $237,800 complete | — 4 open | $35,440 3 open |
32 13 13 · J. Site concrete 1 line | $97,300 complete | — 1 open | $93,800 complete | — 1 open | $90,340 complete |
03 30 40 · K. Placing, hoisting and protection 4 lines | $184,200 complete | $148,000 1 open | $198,100 complete | $98,000 3 open | $150,140 1 open |
| Leveled total From your leveling sheet | $4,345,300 3 gaps open | $4,236,000 7 gaps open | $4,603,500 complete | $4,288,000 14 gaps open | $4,062,690 7 gaps open |
Alternates
The same alternate, bidder by bidder. Tick one to take it from every bidder who priced it.
| Alternate | Tannerbrook Structural Concrete | Maplestone Concrete Constructors | Brindlewood Concrete Structures | Kestrel Ridge Concrete | Ironvale Concrete and Formwork |
|---|---|---|---|---|---|
| deduct $96,000 | deduct $82,000 | deduct $88,000 | not listed | deduct $104,000 | |
| deduct $28,000 | not priced | deduct $36,500 | not listed | not priced | |
| not priced | add $52,950 | add $46,035 | not listed | add $44,010 | |
| add $71,500 | not priced | add $64,000 | not listed | add $58,500 | |
| Adjusted totalbase bid plus every alternate taken | $4,345,300 | $4,236,000 | $4,603,500 | $4,288,000 | $4,062,690 |
Matched by the alternate's number on each bid. A tick here is the same as ticking that alternate in each bidder's row, so the totals and ranking above update with it. Alternates a bidder offered on its own are in that bidder's row.